North Tower Tenant Buildout - Floor 12

North Tower | 555 North Ave, New York, NY 10001

Schedule Overview
Mar
Apr
May
Jun
Jul
Aug
Today
Design Development
Feb 28 - Apr 14
Permit Submission
Apr 15 - May 14
Permit Approval
May 15 - May 31
Construction - Demolition
Jun 1 - Jun 14
Construction - Framing
Jun 15 - Jun 30
Construction - MEP Rough-In
Jul 1 - Jul 14
Construction - Finishes
Jul 15 - Jul 31
Final Inspection
Aug 1 - Aug 8
Move-In
Aug 14
2025
Completed
In Progress
Delayed
Upcoming
Key Milestones

Design Development Approval

Final approval of design development documents

Jun 15, 2025
Completed

Construction Documents Complete

Completion of all construction documentation

Aug 20, 2025
In Progress

Permits Obtained

All necessary permits obtained from local authorities

Sep 10, 2025
Upcoming

Construction Start

Official start of construction activities

Sep 25, 2025
Upcoming

Move-In Date

Tenant move-in and occupancy

Mar 15, 2026