North Tower Tenant Buildout - Floor 12

North Tower | 555 North Ave, New York, NY 10001

Move-In Countdown

104
days

September 30, 2025

Project Milestones

Lease Signed

Jan 15, 2025

Jan 12, 2025

Design Approved

Feb 10, 2025

Feb 15, 2025

Permit Issued

Mar 5, 2025

Mar 8, 2025

Construction Start

Mar 15, 2025

Mar 15, 2025

Furniture/Tech Install

May 20, 2025

In Progress

Substantial Completion

Jun 15, 2025

Pending

Move-In

Jul 1, 2025

Pending

Where We Are Today
Project Completion65%

Current Phase: MEP Rough-in

On schedule

Projected Move-in: August 15, 2025

Originally scheduled for August 1, 2025

Key Updates:

  • Electrical rough-in 80% complete
  • HVAC ductwork installation in progress
  • Plumbing rough-in completed and inspected
  • Drywall delivery scheduled for next week
My Tasks & Approvals
ItemDue DateAssigned ToAction
Final Floor Plan
Review and approve the final floor plan layout
July 10, 2025
Sarah Johnson
Finish Selection
Select finishes for flooring, paint, and fixtures
July 15, 2025
Michael Chen
Signed Permit Application
Upload signed permit application document
July 12, 2025
David Martinez
IT Requirements
Provide detailed IT infrastructure requirements
July 20, 2025
Lisa Thompson
Budget Summary
View Detailed Budget

$850,000

Total Budget

100%

$500,000

TI Allowance

59%

$350,000

Tenant Contribution

41%

Upcoming Events & Site Visits

Weekly OAC Meeting

July 12, 2025
10:00 AM - 11:00 AM
Project Site - Suite 500

Site Walk - MEP Inspection

July 15, 2025
2:00 PM - 3:30 PM
Project Site - Suite 500

Furniture Layout Review

July 20, 2025
11:00 AM - 12:00 PM
Virtual Meeting
Quick Links & Resources

Building Rules & Regulations

Guidelines for construction and tenant improvements

View

Move-in Guidelines

Procedures and requirements for move-in day

View

Tenant Handbook

Comprehensive guide to building services and amenities

View

Contacts Directory

Key contacts for your project and building management

View