Budget

Budget Progress

6%of budget paid
Paid
Committed
Remaining
Forecast (over)

Total Budget

$11,750,000

Approved project budget

Committed

$4,556,000

39% of budget

Paid

$690,000

6% of budget

Remaining

$7,194,000

Available budget

Forecast

$12,337,500

$587,500 over budget

Master Budget

CategoryApprovedCommittedPendingRemaining
Design$1,762,500$630,000$0$1,132,500
Project Management$1,175,000$125,000$55,000$995,000
Construction$8,225,000$2,550,000$950,000$4,725,000
Other$587,500$129,000$117,000$341,500
Total$11,750,000$3,434,000$1,122,000$7,194,000